Risk Probability of Time and Cost on Building Construction Project: A Monte Carlo Simulation

Authors

  • Hafnidar A Rani Department of Civil Engineering, Faculty of Engineering, University of Muhammadiyah Aceh
  • Jurisman Amin
  • Afizah Ayob Faculty of Civil Engineering & Technology, Universiti Malaysia Perlis, 02600 Arau, Perlis, Malaysia
  • Dekky Al Rahmatillah Department of Civil Engineering, Faculty of Engineering, Universitas Muhammadiyah Aceh, Jl. Muhammadiyah No. 91, Banda Aceh 23245, Indonesia

DOI:

https://doi.org/10.31629/jit.v3i2.5192

Keywords:

Probability, Risk, Time, Cost, Monte Carlo

Abstract

Construction project has never been avoided by not only low risk but also high risk. It can also occur in building and infrastructure construction project of Aceh Regional Intelligent Agency (BINDA) office complex. The complex structural works can impact the significant risk to the project construction process. To minimize the risk, it is required to review the risk analysis to the time and the cost. The problem of the research was how many probabilities of the highest risk by using Monte Carlo. The objective of the research was to analyze the highest risk probability percentage of time and cost in building construction project by using Monte Carlo simulation. Sampling technique used was census sampling by using 18 respondents. The variables used were contractual risk, construction risk, material and equipment risk, design and technology risk, and force majeure risk. The output of risk acceptability level analysis by using probability and impact found that the dominant risk in undesirable category is wrong implementation as the highest value of 7.50 risk value. The simulation output of Monte Carlo by using @risk software resulted that project duration time was 460 days on 99% probability. For probability distribution of cost estimation resulted that budget plan estimation was IDR 1,991,000,000 on 99% probability, so the project cost estimation can get the benefit as 1.00% by using @risk simulation. Therefore, the response provided is coordination to supervision consultant and owner.

Downloads

Published

2022-10-31

How to Cite

Rani, H. A., Amin, J. ., Ayob, A. ., & Rahmatillah, D. A. . (2022). Risk Probability of Time and Cost on Building Construction Project: A Monte Carlo Simulation. Journal of Innovation and Technology, 3(2), 60–68. https://doi.org/10.31629/jit.v3i2.5192

Issue

Section

Articles